CURRENT WATER PROJECTS

The G.A.V.E. Water Project has begun construction for the Adzokoe-Peki village as of 28NOV24

This project is complete - Praise the Lord! 3000 villagers with water in the village

George Arhin team arriving onsite Peki village

Excavation has begun

10k liter polytanks

The Borehole team meets the Adzokoe-Peki Chief to discuss the G.A.V.E. Water project

30DEC24 - The Polytanks are on site and placed. Last step is to install the pump now that all components are secured

3JAN25 - The G.A.V.E. Water project is installed and operational - THank God!!

This village had an existing covered/inoperable borehole. No drilling necessary. This cuts down the project costs. This inoperable pump will be dismantled and a new solar powered pump installed. The aquifer has tested good!

Platform construction is in progress - Junior High School students of Adzokoe-Peki are assisting with gravel collection for filling the platform that will hold the 2x10k liter water storage tanks

3JAN25 - A couple teen girls from village using newly installed water facility - There walk for water has ended, Praise God! Water Commissioning picture coming early next week.

A family of men and boys fetching water. Normally this activity is for the women and girls. I asked why men and boys are fetching water - hear response below

Old pump dismantled ready for new solar-powered pump

Akonoma Village Quote for G.A.V.E. Water project 99,0005.00 GHS = 6,334.29 USD

Borehole survey/geological study

Borehole drilling and well construction

Solar powered water pump installation

Solar panel installation

Water Storage Tank installation

Water storage tank platforms

Below it the quote for installing the G.A.V.E. Water Project in the Azodoke-Peki village - 84.085.00 GHS = 5,146.00 USD

NOTE: This village had an existing inoperable borehole so NO DRILLING Required! Reduces project cost

Below is a request for an irrigation system for a greenhouse in Tamale, Ghana

G.A.V.E PROJECT QUOTES

Current - Irrigation system Nantun Sapalo Village

Recently completed - Adzokoe-Peki Village

Recently completed - Akonoma Village

Brafoyaw Village Quote for G.A.V.E. Water project 101,585.00 GHS = 6,482.77 USD

Borehole survey/geological study

Borehole drilling and well construction

Solar powered water pump installation

Solar panel installation

Water Storage Tank installation

Water storage tank platforms

CANCELLED Due to poor acquifer

UPCOMING WATER PROJECTS

Village Name:

Adzokoe-Peki Village - COMPLETE - JAN 2025

Brafoyaw Village - Raising funds - Cancelled - Aquifer is not good

Nantong-Sapalo, Greenhouse irrigation- RAISING FUNDS

Akonoma Village COMPLETE - OCT 2024

Village Contact:

Innocent Kelvin Coffie

Abubakar Sadiq Mohammed

Mr. Samuel Yawson

Village Location:

Volta Region

Tamale

Cape Coast

#of Villagers

Over 3k

Over 4k

Over 10k

October 2024 - It was determined after 20 drilling attempts in Brafoyaw village that the aquifer is not good so this village project is cancelled.

September 2024

Both of these villages are located just outside of Cape Coast in the Central region of Ghana. They are both in need of the G.A.V.E. Water Package: Borehole, Solar Panel, Water Pump, 2x 10k liter Water Storage Tanks and the platform for the tanks

Akonoma Village has a school in the village and the water package will assist greatly - Nearing completion

Brafoyaw Village has a clinic that needs completing. Once done the Government will supply doctors, nurses and medical equipment. See Quote (forthcoming) - Please Donate

Akonoma Water Project - COMPLETE

14OCT24 Akonoma School Children thanking G.A.V.E. for water project!

2024 COMPLETED PROJECTS

The Akanoma Village G.A.V.E. Water project is in progress:

  • Borehole truck arrived on-site and began drilling

  • Water is present

  • Water Pump is installed

  • Platform construction in progress

  • Solar Panels procured

  • Poly tanks onsite and platform construction almost complete

Let There Be Water!!

Recently Completed Project

Janikura village water pump replacement and solar panel installation

Quote for project - 20,500.00 GHS = 1,411,00 USD (At time of transfer in July 2024)

Janikura Village replacement water pump and solar panel installation

Project is complete!